This Geothermal project was for a new 2 story home in West End, NC. A new 4.0 ton unit was installed with new duct work by Sunbelt Mechanical - Aberdeen, NC. 9 - 90' boreholes with 1 - 1" x 95' loop in each borehole.
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
Drilling the 1st of 9 - 90' boreholes with mud rotary.
|
|
|
|
All 9 boreholes completed.
|
|
|
|
|
|
 |
|
 |
|
|
|
1" vertical loop laid out for placement in borehole.
|
|
|
Mud rotary drilling.
|
|
|
|
|
|
|
 |
|
 |
|
|
|
1" vertical loop with rebar attached for weight and to keep loop straight.
|
|
|
|
Loop grouted in borehole with Thermal-Enhanced grout.
|
|
|
|
|
|
 |
|
|
|
Vertical loops grouted with Thermal-Enhanced Grout.
|
|
|
|
|
|
|
|