This Geothermal project was for a 1 story 1,563 sqft. home with 1,563 basement in Statesville, NC, built in 1949. A new 4.0 ton Trane Geothermal unit was installed with new duct work by JP'S Plumbing & Heating - Statesville, NC. 4 - 170' boreholes with 1 - 3/4 x 175' loop in each borehole.
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
All 8 loops were drilled in the proposed driveway.
|
|
Back of new 7,000 sqft. residence
|
|
|
|
|
|
 |
|
 |
|
|
|
All 8 loops were drilled in the proposed driveway.
|
|
Header line from loops to the garage. This is where the circulating pump will be installed.
|
|
|
|
|
|
 |
|
 |
|
|
|
Header line from garage to proposed trench to vertical loops.
|
|
View from garage door of all 8 vertical loops installed.
|
|
|
|
|
|
|
|
|
|